Kenyan President Uhuru Kenyatta has launched a 50 MW solar power farm located in Garissa, northeast region, with the plant being one of the largest photovoltaic electricity stations in Africa.
The project was designed and constructed by the EPC contractor China Jiangxi Corporation for International Economic and Technical Co-operation (CJIC), in conjunction with Kenya's Rural Energy Autho. . .
Posted on :Monday , 16th December 2019
Construction of the Murang'a substation in Kenya nears completion. Kenya Power Company (KPC) Manager, Eng. Harrison Kamau, confirmed the report and said that the project will be completed and equiped for commissioning by end of December.
The 7.5MVA substation aims to strengthen power supply in Murang’a. It is being subsidized at Kenya Power Company (KPC) at a cost of US $3m. At pre. . .
Posted on :Wednesday , 4th December 2019
China Aerospace Construction Group has disclosed construction of a 40-km 400kV Konza-Isinya transmission line, which will power Konza City as well as Kajiado, Makueni, and Machakos counties.
The project, which is being contracted in partnership with Kenya’s ministry of energy, is focused to ensure constant supply of power for the proposed smart city located in Machakos.
The . . .
Posted on :Tuesday , 19th November 2019
Kenya's ministry of energy and a Chinese firm, China Aerospace Construction Group, have launched the construction of an extensive power transmission project outside the capital, Nairobi.
Once concluded, the 40 km, 400 Kva Konza-Isinya Transmission Line Project will ensure reliable power supply for Konza Technopolis, south of Nairobi.
Li Naihong, deputy general manager China Aerosp. . .
Posted on :Monday , 18th November 2019
Kenya energy generator, KenGen has signed a Kshs 5.8 Bn deal to drill 12 geothermal wells in Ethiopia and boost the countries energy needs. In contract with Ethiopian independent power producer Tulu Moye Geothermal Operations (TMGO) PLC, KenGen will also grant water supply system and equipment.
After KenGen, won a contract to drill geothermal wells for the Ethiopian Electric Power (EEP) . . .