Edenville Energy to proceed with Rukwa coal to power project in Tanzania

Posted on : Wednesday , 19th July 2017

 n early 2017 a new Power Master Plan Update was released by the Government of Tanzania that included the Edenville Energy project.

 
This plan is now being progressively rolled out by the government of Tanzania to provide further power generation and transmission for the country over the long term up to 2040.
 
The project has already had a feasibility study carried out in 2015 for a 120 MW power generation facility and the Ministry of Energy has indicated a larger facility of up to 300 MW can be constructed at Rukwa, assuming technical, financial and commercial parameters can be satisfied.
The 120 MW project returned an NPV10 of US$252 million and an IRR of 23% from recent independent financial modelling carried out in late 2016.
 
In January 2017 Edenville Energy signed a Memorandum of Understanding with Sinohydro Corporation of China to complete a bankable feasibility study on the project.
 
Edenville Energy and Sinohydro will be looking at all options to optimise the power plant size and to source suitable funding from recognised financial institutions for construction of the Project.
 
In parallel with this, talks will take place with The Tanzanian Electric Supply Company to finalise the power purchase agreement and associated transmission infrastructure that will be needed to take the electricity.
 
Edenville Energy holds 100% of Edenville Power Tanzania, the company registered in Tanzania to develop and operate the project.
 
Edenville Energy through its Tanzanian subsidiary Edenville International Tanzania also holds the Mkomolo mining licence ML562/2016 and a 90% interest in the coal deposits at Rukwa.
 
New access road permit granted for coal mine
 
Edenville Energy has also received permission to upgrade and where necessary construct, a new access road that will connect the site with the main north south sealed highway to the west of the project.
 
The road will be approximately 16 km long and allow coal trucks to reach the site more efficiently than the current transport infrastructure. Ultimately this road will also be used as part of the power plant access infrastructure.
 
Work is commencing on the road immediately and Edenville Energy expects a usable road to be completed by the end of June 2017.
 
“The request from the Ministry of Energy and Minerals is a very significant step forward in the timeline for the development of the project,” says Edenville Energy CEO, Rufus Short.
 
“The project can now move forward, working alongside the Tanzanian authorities, to ultimately provide significant electricity expansion to the country,” he continues.
 
The start-up of the coal mine to provide commercial coal sales will undoubtedly assist the power plant development as this will give a significantly greater understanding of the coal that will be used for power generation.
 
“The next few years will be an extraordinarily busy and transformative time for the company as both the mine and the power plant are developed, and I look forward to providing regular updates as and when appropriate,” concludes Short.

Source : https://www.miningreview.com

OUR ASSOCIATES

VIEW MORE

EXPOGROUP

Expogroup is a full service exhibition organiser with over eighteen years experience in International.Trade Exhibitions and Events. Our current portfolio includes 20 annual exhibitions from a diverse range of industries being held across the Middle East & Africa.

EXPOGROUP © 1996 - 2024 | Privacy Policy

Find us here

Subscribe Newsletter

Join our mailing list and receive latest news and advice from us in our monthly Newsletter

Yes, I would like to receive Expogroup E-newsletters

Instant Reply